📖 Code of Practice · study guide

How to Safely Remove Asbestos

A plain-English walkthrough of the model Code of Practice: How to safely remove asbestos. This is a step up from awareness — it's about doing removal work legally and safely.

👋 Start here

This guide distils the model Code of Practice: How to safely remove asbestos. A Code of Practice is approved under the WHS Act — following it helps you comply with the law, and courts can use it as evidence of what's reasonably practicable.

Read the words carefully: “must”, “requires” and “mandatory” = a legal requirement. “Should” = strongly recommended. “May” = optional.

There's a companion Code — How to manage and control asbestos in the workplace — which covers identifying asbestos and deciding whether removal is even the right control. Often, if ACM is in good condition, the safest choice is to leave it undisturbed.

1 · Who's responsible

More than one person can hold a duty at the same time. The key duty holders:

PCBU (the business)

Must eliminate the risk from asbestos removal — or minimise it so far as reasonably practicable. Must ensure airborne asbestos exposure is eliminated/minimised and the exposure standard is not exceeded. Must consult workers.

Officers (directors/managers)

Must exercise due diligence — ensure the business has and uses the right resources and processes to control the risk.

Workers

Take reasonable care for their own and others' safety, follow reasonable instructions, and cooperate with policies and procedures.

Others at the workplace

Visitors and neighbours take reasonable care and follow reasonable instructions.

Consult, train, instruct. The PCBU must consult affected workers, and provide information, training, instruction and supervision suitable to the work — including the correct use, storage and maintenance of PPE. Training should be delivered by a competent person.

2 · Do you need a licence?

The licence you need depends on the type and amount of asbestos, ACM or asbestos-containing dust (ACD) being removed.

Class A

Any amount of any asbestos — including friable asbestos/ACM, any ACD, and any non-friable ACM. The only licence that can remove friable asbestos.

Class B

Any amount of non-friable asbestos/ACM, plus the ACD associated with removing it. Cannot remove friable asbestos.

No licence

Up to 10 m² of non-friable asbestos/ACM, and only minor associated ACD. Still must follow the controls in this Code.

Licensed asbestos assessor: for Class A work, an independent licensed assessor must do the air monitoring, the clearance inspection and issue the clearance certificate.

Note: some jurisdictions vary — e.g. in the ACT the 10 m² concession is applied differently. Always check your regulator's rules.

3 · Health monitoring

The PCBU must provide health monitoring to workers at risk of asbestos exposure — whether doing licensed removal, ongoing unlicensed removal, or other asbestos-related work.

  • Includes a baseline medical and standardised respiratory function tests.
  • Must be done before a worker starts licensed removal, and at least every 2 years thereafter.
  • Carried out by (or under) a registered medical practitioner experienced in health monitoring.
  • The PCBU pays all costs.
  • Reports are kept confidential for at least 40 years; not disclosed without the worker's written consent.

4 · Before you start (licensed work)

Before a single sheet comes off, licensed removal work has a clear set-up checklist:

Supervisor — a competent asbestos removal supervisor must be present or readily available.
Get the asbestos register for the workplace and review it.
Prepare an Asbestos Removal Control Plan (ARCP) — before work starts.
Inform the client, the person in control of the workplace, and affected people.
Notify the regulator in writing at least 5 days before starting.

The ARCP

Identifies the specific control measures and how the work will be done safely. Keep it readily accessible on site for the whole job; keep it 2 years if a notifiable incident occurs.

The 5-day notice

Includes the removalist & supervisor details, assessor, client, address, dates, whether it's friable or non-friable, quantity, and worker competencies. In a genuine emergency (e.g. burst asbestos-lagged pipe) work can start immediately — notify by phone, then in writing within 24 hours.

5 · Setting up the area

  • Erect signs showing where removal work is happening and barricades to mark out the asbestos area.
  • Limit access — only removal workers, associated people, and those legally allowed (e.g. inspectors) may enter.
  • Set up decontamination facilities for people, plant and equipment before work begins.

6 · Safe removal methods

The whole game is keeping fibres out of the air. Two golden rules and a short list of tool do's and don'ts:

💧 Use the wet method

Wherever reasonably practicable, keep the material wet (fine water spray) to stop fibres becoming airborne. Dry removal is a last resort with extra controls.

🚫 No dust-makers

Don't use anything that grinds material into airborne dust — no power sanders/grinders, no compressed air, no high-pressure water blasting.

  • Prefer hand tools and non-powered methods; remove whole sheets/components intact where possible.
  • Use a HEPA-filtered, Class H asbestos vacuum for clean-up — never a normal vacuum. Keep it decontaminated.
  • Clean up as you go; never sweep or use anything that re-suspends dust.

7 · PPE & RPE

Protective clothing

Disposable coveralls (type 5, category 3), one size too big to stop seams ripping, with the hood over the RPE straps and no cuffs that trap dust. Plus gloves and suitable footwear.

Respiratory protection (RPE)

Must be correctly selected for the job and fit tested. You must be clean-shaven for a tight-fitting respirator to seal. Half-face (P1/P2), powered, or full-face depending on the risk.

PPE is the last line of defence — it backs up the wet method, tools and enclosures; it doesn't replace them.

8 · Decontamination

Nothing contaminated leaves the area without being cleaned. The PCBU must provide facilities to decontaminate the work area, plant, workers and associated people.

  • Personal decon: a staged process — remove/HEPA-vacuum coveralls, wash, and remove RPE last (large jobs use a 3-stage unit: dirty → shower → clean).
  • Equipment decon: tools and plant are cleaned before leaving, or sealed in a container whose outside is decontaminated and labelled.

9 · Waste & disposal

  • Asbestos waste must be contained and labelled (GHS) before it leaves the removal area.
  • Use heavy-duty double-bagging / lined bins; keep wet; don't overfill.
  • Dispose as soon as practicable at a site authorised to accept asbestos waste.
  • Disposable PPE is sealed, labelled and disposed of with the waste at the end of the job.

10 · Air monitoring

Air monitoring measures airborne fibres — either control monitoring (are the controls working?) or exposure monitoring (a worker's breathing zone). It uses the membrane filter method.

  • Mandatory for all friable asbestos removal — including before an enclosure is dismantled.
  • The workplace exposure standard is 0.1 fibres/mL (8-hour time-weighted average).
< 0.01 f/mLControls are working — continue.
0.01 – 0.02 f/mLReview & investigate the controls, find the cause.
> 0.02 f/mLSTOP removal work, control the release, and notify the regulator.

11 · Clearance & re-occupation

The area cannot be re-occupied until a clearance certificate is issued. It confirms the area (and the space around it) is free of visible asbestos contamination.

  • Done by an independent licensed asbestos assessor for Class A (friable) work, or an independent competent person for non-friable work over 10 m².
  • “Independent” = not involved in doing that removal job.
  • A visual inspection checks for dust and debris; if air monitoring is done, results must be below 0.01 fibres/mL.
  • Barricades stay up until the final clearance certificate is issued.

12 · Friable & special jobs

Friable asbestos is the highest-risk work — Class A only, with the strongest controls.

Large-scale: full enclosure

Build and smoke-test a sealed enclosure kept under negative pressure with HEPA-filtered exhaust units, so air flows in, not out. Bulk-strip and clean inside; only dismantle after clearance monitoring passes.

Small-scale methods

Mini-enclosure (a small sealed booth), glove bag (a sealed bag you work through, e.g. on pipe lagging), and wrap-and-cut (wrap the item, then cut and remove it intact).

The Code also covers specific jobs: asbestos-contaminated soil, friable asbestos on hot surfaces, and asbestos in plant, pipes and pits.

🎯 Summary — the key numbers

10 m²
Non-friable limit without a licence
5 days
Notice to the regulator
0.1 f/mL
Exposure standard (8-hr TWA)
0.01 f/mL
Clearance / control target
  • Friable = Class A only. Non-friable = Class A or B; up to 10 m² needs no licence (but same controls).
  • Plan & notify: ARCP before work, 5 days' notice, get the register, supervisor present.
  • Keep fibres down: wet method, hand tools, HEPA H-class vacuum — never power tools or compressed air.
  • Contain & clean: signs/barricades, decontamination, double-bagged labelled waste to an authorised site.
  • Prove it's clean: independent clearance certificate before anyone goes back in.
📗

That's the removal Code covered

Try the free practice test any time — and when you're confident, register your assessment with the trainer.

📝 Try the practice test → ← Awareness guide

Adapted from the Safe Work Australia model Code of Practice: How to safely remove asbestos (July 2020), used under a Creative Commons Attribution-Noncommercial 4.0 licence. This is a study summary — for legal purposes always refer to the full Code and your jurisdiction's WHS laws (in the ACT, WorkSafe ACT).

↑